CISA (Certified Information Systems Auditor) is a ISACA certification. IT Cert Ready offers 1,800 practice questions with domain quizzes, full mock exams, and detailed explanations. Practice by official domain with 5 blueprint-aligned domains.

Official exam domain weights

Verified blueprint weights from the official exam outline.

  • Domain 1 · Auditing Process · 18%
  • Domain 2 · Governance & Management · 18%
  • Domain 3 · Acquisition, Development & Implementation · 12%
  • Domain 4 · Operations & Business Resilience · 26%
  • Domain 5 · Protection of Information Assets · 26%

Sample CISA practice questions

Preview realistic multiple-choice items from the IT Cert Ready question bank. Expand each answer for the correct choice and explanation—the same format used in domain quizzes and mock exams.

  1. Sample question 1 · Governance & Management of IT

    The Ridgecroft County Department of Social Services recently migrated its legacy case management system to a cloud-based platform operated by a third-party vendor, CloudServe Solutions. The contract was executed under an emergency procurement waiver due to budget cycle pressures, bypassing the standard vendor evaluation committee. Eighteen months into the contract, an IS auditor reviewing vendor management practices discovers that: (1) no formal security assessment of CloudServe was conducted prior to contract award; (2) the contract contains no data residency clauses despite the department handling federally protected beneficiary data; (3) CloudServe's subcontractor, DataVault Inc., processes backup data in an offshore jurisdiction without the department's knowledge; and (4) the department's IT manager verbally approved the subcontracting arrangement after the fact. The department's legal counsel confirms that the offshore processing likely violates the state's data sovereignty statute. Given the audit findings, which control gap represents the MOST significant risk to the department's compliance posture and should be the primary focus of the IS auditor's remediation recommendation?

    • A. The absence of a formal security assessment prior to contract award, because it prevented the department from evaluating CloudServe's technical controls before granting access to sensitive systems.
    • B. The lack of data residency and subcontracting oversight clauses in the contract, because it created an unenforceable legal position against a vendor arrangement that currently violates state data sovereignty law.
    • C. The verbal approval of the subcontracting arrangement by the IT manager, because it bypassed the department's change management process and created an undocumented governance decision.
    • D. The use of an emergency procurement waiver, because it circumvented the vendor evaluation committee and established a pattern of bypassing established governance controls.
    View answer & explanation

    Correct answer: B. The lack of data residency and subcontracting oversight clauses in the contract, because it created an unenforceable legal position against a vendor arrangement that currently violates state data sovereignty law.

    [Domain 2 - Governance & Management of IT, Subtopic B - IT Management - Area 2 - IT Vendor Management] Core Concept: In vendor contract management, the enforceability of contractual protections is the foundational mechanism through which an organization can compel vendor compliance with legal and regulatory requirements. Correct Answer (B): The lack of data residency and subcontracting oversight clauses in the contract, because it created an unenforceable legal position against a vendor arrangement that currently violates state data sovereignty law. While all four findings represent genuine control gaps, the absence of data residency and subcontracting oversight clauses is the most critical because it has already produced a confirmed statutory violation - offshore processing of protected beneficiary data - for which the department currently has no contractual remedy. Without enforceable contract language, the department cannot legally compel CloudServe to cease the arrangement, seek indemnification, or impose penalties Why the other options are incorrect: Option A: Though important, addresses a pre-contract evaluation gap that is now historical; the more urgent issue is the active compliance breach. Option C: Is a governance process failure but is secondary to the legal exposure it enabled. Option D: While a root cause, is also historical and does not directly address the ongoing statutory violation. ISACA's IT vendor management framework emphasizes that contracts must explicitly address legal and regulatory requirements - including data handling, subcontracting rights, and jurisdiction - as the primary instrument for managing third-party risk.

  2. Sample question 2 · Information Systems Operations & Business Resilience

    A state-level department of labor administers unemployment benefit payments through a legacy mainframe batch processing environment. The department's IT operations team runs nightly job schedules that calculate and authorize benefit disbursements. An IS audit reveals: (1) Job scheduling parameters are stored in flat-file control decks that have not been reviewed or formally approved since the system was implemented nine years ago. (2) Three instances in the past fiscal year involved batch jobs completing with return codes indicating partial failure; in each case, operators restarted the jobs without logging a formal incident or notifying the application owner. (3) The department's IT service management policy requires that any production job failure resulting in incomplete data processing be treated as a Priority 1 incident with mandatory notification to the business unit owner within one hour. (4) Post-audit interviews reveal that operators were unaware of this policy requirement, as no formal operator training on incident classification had been conducted since the policy was updated two years ago. (5) In one of the three cases, approximately 340 benefit recipients received duplicate payments that required manual recovery efforts costing an estimated $47,000. Based on the audit findings at the state department of labor, which condition represents the MOST direct failure of IT service management alignment with organizational requirements that the IS auditor should escalate?

    • A. The job scheduling control decks have not been formally reviewed or reapproved in nine years, indicating that production automation parameters may no longer reflect current business processing rules.
    • B. Operators restarted failed batch jobs without classifying them as Priority 1 incidents or notifying business unit owners, directly violating the incident management policy and resulting in a material financial error that went undetected through proper channels.
    • C. No formal operator training on incident classification has been conducted since the policy was updated, indicating a training and awareness gap that undermines the effectiveness of the incident management framework.
    • D. The IT service management policy was updated without a corresponding communication plan to affected operations staff, suggesting a deficiency in change management procedures for policy governance.
    View answer & explanation

    Correct answer: B. Operators restarted failed batch jobs without classifying them as Priority 1 incidents or notifying business unit owners, directly violating the incident management policy and resulting in a material financial error that went undetected through proper channels.

    [Domain 4 - Information Systems Operations & Business Resilience, Subtopic A - Information Systems Operations - Area 3 - Job Scheduling and Production Process Automation] Core Concept: Problem and Incident Management within IT service management frameworks requires that production failures be correctly classified, escalated, and communicated according to established policy - particularly when those failures affect business-critical processes such as government benefit disbursements. Correct Answer (B): Operators restarted failed batch jobs without classifying them as Priority 1 incidents or notifying business unit owners, directly violating the incident management policy and resulting in a material financial error that went undetected through proper channels. Why the other options are incorrect: Option A: Is a legitimate finding related to job scheduling and production process automation governance, but it represents a potential risk rather than a confirmed harm. Option C: . Auditors must distinguish between root causes, contributing factors, and the primary control failure with the greatest organizational consequence. Option D: Is speculative - the audit evidence does not confirm that a communication plan was absent; it only confirms that operators were unaware, which is better explained by.

  3. Sample question 3 · Information Systems Acquisition, Development & Implementation

    Vantara Digital, a fast-growing European e-commerce marketplace operating under GDPR, is building a proprietary supplier portal to automate onboarding and compliance verification for its 400+ third-party vendors. The business case, submitted by the Head of Procurement, estimates €1.8 million in savings over four years from reduced manual onboarding effort and compliance penalties. The IS auditor notes that the business case includes a high-level financial model but lacks a defined set of success criteria, contains no risk register addressing supply-chain data exposure, and does not reference any regulatory compliance objectives despite GDPR obligations requiring documented vendor due diligence. The project is classified as Tier 1 (high business impact) under Vantara's internal project governance framework. While evaluating the Vantara Digital business case, the IS auditor determines that it omits regulatory compliance objectives and contains no measurable success criteria. Which conclusion best reflects the auditor's assessment of whether this business case adequately supports informed decision-making aligned with business objectives?

    • A. The business case is adequate because the €1.8 million savings estimate demonstrates a positive return on investment, and regulatory compliance can be addressed during the implementation phase through a separate compliance workstream.
    • B. The business case is inadequate because the omission of GDPR-related compliance objectives and the absence of measurable success criteria prevent stakeholders from evaluating whether the system will achieve its intended business outcomes or satisfy regulatory obligations that are core to the organization's operating environment.
    • C. The business case is inadequate primarily because it was not reviewed by the legal department, and the auditor should recommend that legal sign-off be obtained as a compensating control before the project proceeds.
    • D. The business case is adequate for a Tier 1 project because the project governance framework itself provides sufficient oversight controls, making detailed success criteria within the business case redundant.
    View answer & explanation

    Correct answer: B. The business case is inadequate because the omission of GDPR-related compliance objectives and the absence of measurable success criteria prevent stakeholders from evaluating whether the system will achieve its intended business outcomes or satisfy regulatory obligations that are core to the organization's operating environment.

    [Domain 3 - Information Systems Acquisition, Development & Implementation, Subtopic A - Information Systems Acquisition and Development - Area 1 - Project Governance and Management] Core Concept: A business case must articulate not only financial returns but also the full spectrum of business objectives the system is intended to achieve - including regulatory compliance obligations that are material to the organization's operating environment. For Vantara Digital, GDPR vendor due diligence is not optional; it is a legal obligation that directly shapes the purpose and design of the supplier portal. Correct Answer (B): The business case is inadequate because the omission of GDPR-related compliance objectives and the absence of measurable success criteria prevent stakeholders from evaluating whether the system will achieve its intended business outcomes or satisfy regulatory obligations that are core to the organization's operating environment. The omission of GDPR compliance objectives means the business case cannot demonstrate alignment with a critical business objective. Additionally, without measurable success criteria, there is no basis for post-implementation evaluation of whether the system delivered its intended value - a fundamental requirement of sound business case design per ISACA BAI01 and COBIT APO05 Why the other options are incorrect: Option A: Defers compliance to implementation; compliance objectives must be established at the business case stage to shape system requirements. Option C: Focuses on a procedural control (legal sign-off) rather than the substantive content deficiency. Option D: Conflates project governance oversight with the content requirements of a business case; governance frameworks do not substitute for defined success criteria within the business case itself.

  4. Sample question 4 · Information Systems Auditing Process

    Northgate Municipal Tax Administration (NMTA), a small government agency in a rural jurisdiction, processes property tax records using a legacy mainframe system that has not received vendor security patches for over four years. A prior IS audit flagged a high-risk finding related to the absence of a formal vulnerability management program, noting that unpatched systems exposed sensitive taxpayer financial data to exploitation. Management's agreed remediation plan included: (1) engaging a third-party vendor to assess mainframe patch feasibility within 60 days, and (2) implementing network segmentation to isolate the mainframe within 120 days. Fourteen months later, during follow-up, the auditor receives the third-party feasibility report - which concluded that patching is technically infeasible without a full system replacement - and a network diagram showing the mainframe now sits behind a dedicated firewall VLAN. However, the firewall ruleset review reveals 14 overly permissive inbound rules that allow broad internal network access to the mainframe, effectively negating the segmentation intent. During post-audit follow-up, how should the IS auditor evaluate the adequacy of NMTA's remediation efforts relative to the original high-risk finding?

    • A. Accept the remediation as complete because management fulfilled both committed action items: the feasibility study was delivered and network segmentation was physically implemented as documented in the network diagram.
    • B. Accept the feasibility study outcome as a valid basis for closing the patching component, but treat the network segmentation as insufficiently implemented and keep the finding open pending correction of the firewall ruleset.
    • C. Close the finding entirely and issue a new, separate audit observation about the firewall ruleset, since the original finding was scoped to vulnerability management and the firewall issue represents a distinct control domain.
    • D. Immediately recommend system decommissioning to the agency director as the only viable risk treatment option, since patching is infeasible and segmentation has failed.
    View answer & explanation

    Correct answer: B. Accept the feasibility study outcome as a valid basis for closing the patching component, but treat the network segmentation as insufficiently implemented and keep the finding open pending correction of the firewall ruleset.

    [Domain 1 - Information Systems Auditing Process, Subtopic B - Execution - Area 1 - Audit Project Management] Core Concept: Effective post-audit follow-up requires the auditor to assess whether the underlying risk - not just the surface-level action items - has been sufficiently addressed. The original risk was unauthorized access to sensitive taxpayer data via an unpatched legacy system. The feasibility study legitimately establishes that patching is not viable, which is an acceptable finding that management must now address through alternative risk treatment (e.g., system replacement planning or enhanced compensating controls). That component can be acknowledged as addressed in terms of the committed action. However, the network segmentation - the primary compensating control intended to reduce exposure - is functionally ineffective due to 14 overly permissive firewall rules that allow broad internal access. Correct Answer (B): Accept the feasibility study outcome as a valid basis for closing the patching component, but treat the network segmentation as insufficiently implemented and keep the finding open pending correction of the firewall ruleset. The auditor must evaluate substance over form: a VLAN exists on paper, but the control objective (isolation of the mainframe) has not been achieved. Therefore, the finding must remain open for the segmentation component Why the other options are incorrect: Option A: Completing action items does not equate to risk reduction if the implemented controls are ineffective. Option C: Artificially separating a directly related control failure into a new observation to close the original finding misrepresents remediation status and undermines audit integrity. Option D: Recommending a specific risk treatment (decommissioning) exceeds the auditor's role during follow-up; the auditor assesses control effectiveness and reports findings - management decides on risk treatment options.

  5. Sample question 5 · Governance & Management of IT

    Vantara Commerce, a fast-growing online fashion retailer headquartered in the United Kingdom and subject to UK GDPR, recently expanded its supplier base to include 30 overseas manufacturers who are granted limited access to Vantara's product management portal. An IS auditor conducting a governance assessment finds that the company's enterprise risk management policy assigns ownership of 'supplier access risks' to the IT department. However, interviews reveal that the IT team interprets its role as purely technical - provisioning and deprovisioning accounts - while decisions about which suppliers should receive access, at what privilege level, and under what contractual conditions are made ad hoc by the merchandising team. The company's data governance policy classifies supplier-accessible product data as 'Confidential,' but no control standard specifies who must approve access to Confidential data for external parties. A recent internal review flagged two instances where former suppliers retained active portal credentials for more than 60 days after contract termination. When assessing whether Vantara Commerce has adequately defined ownership of IT risk, controls, and standards related to supplier access, what should the IS auditor identify as the primary governance failure?

    • A. The IT department is performing access provisioning tasks that should be delegated to the merchandising team, creating a segregation-of-duties conflict.
    • B. The absence of a control standard governing approval authority for external-party access to Confidential data means that risk ownership, while nominally assigned, is operationally unenforceable and produces inconsistent outcomes.
    • C. The two instances of delayed credential revocation indicate that the IT team is not fulfilling its assigned risk ownership responsibilities and should be replaced as the designated owner.
    • D. Vantara's UK GDPR obligations require a Data Protection Officer to own all supplier-related data risks, and the current assignment to IT violates regulatory requirements.
    View answer & explanation

    Correct answer: B. The absence of a control standard governing approval authority for external-party access to Confidential data means that risk ownership, while nominally assigned, is operationally unenforceable and produces inconsistent outcomes.

    [Domain 2 - Governance & Management of IT, Subtopic A - IT Governance - Area 5 - Enterprise Risk Management] Core Concept: Assigning risk ownership on paper without establishing the supporting control standards, approval authorities, and decision rights that make ownership operational is a fundamental IT governance deficiency. Correct Answer (B): The absence of a control standard governing approval authority for external-party access to Confidential data means that risk ownership, while nominally assigned, is operationally unenforceable and produces inconsistent outcomes. In this scenario, IT nominally owns 'supplier access risks,' but the absence of a control standard defining who must approve Confidential data access for external parties means the ownership assignment cannot be exercised in practice - access decisions default to an informal, ad hoc process in the merchandising team Why the other options are incorrect: Option A: Mischaracterizes the situation; provisioning is an appropriate IT function, and the real problem is not who provisions accounts but who authorizes access decisions. Option C: Treats the credential revocation failures as evidence that IT should be replaced rather than as a symptom of the missing control standard and unclear decision rights. Option D: Overstates the regulatory requirement; UK GDPR requires a DPO for certain processing activities but does not mandate that the DPO own all supplier-related IT risks. The core finding is that nominal ownership without enforceable control standards and defined approval authority renders the governance structure ineffective, which is precisely what Task 14 directs auditors to evaluate.

CISA exam prep FAQ

What is the passing score for the CISA exam?
The CISA exam uses a scaled score. A common published passing threshold is 450 out of 800 points. Always confirm the current requirement on the official ISACA exam guide before you sit for the test.
How many questions are on the CISA certification exam?
The live CISA exam typically includes 150 questions with about 4 hours on the clock. Formats can vary by delivery mode and exam update.
How do domain quizzes help with CISA exam prep?
Domain quizzes on IT Cert Ready let you practice CISA one blueprint domain at a time across 5 official exam domains. You get immediate feedback, detailed explanations, and can revisit weak areas before taking a full timed mock exam.
How many CISA practice questions are on IT Cert Ready?
IT Cert Ready includes 1,800 published CISA practice questions with domain quizzes, full-length mock exams, and answer explanations mapped to the official outline.